(IGP) CSAT Paper - II : Basic Numeracy - MCQ 6
Basic Numeracy (MCQ - 6)
1. Sixteen men can complete a work in twelve days.
Twenty-four children can complete the samework in eighteen days. Twelve men and
eight children started working and after eight days three more children joined
them. How many days will they now take to complete the remaining work?
1. 5 days
2. 4 days
3. 10 days
4. 9 days
2. Twenty-four men can complete a work in sixteen days.
Thirty-two women can complete the same work in twenty-four days. Sixteen men and
sixteen women started working and worked for twelve days. How many more men are
to be added to complete the remaining work in 2 days?
1. 18 men
2. 24 men
3. 36 men
4. 50 men
3. 5 men and 2 boys working together can do four times as much work as a
man and a boy. Working capacities of a woman and a boy are in the ratio:
1. 1 : 2
2. 2 : 1
3. 1 : 3
4. 6 : 7
4. If 12 men and 16 boys can do a piece of work in 5 days; 13 men and 24
boys can do it in 4 days, then the ratio of the daily work done by a man to that
of a boy is:
1. 2 : 1
2. 3 : 1
3. 3 : 2
4. 6 : 7
5. 4 men and6 women can complete a work in 8 days, while 3 men and7 women
can complete it in 10 days. In how many days will 10 women complete it?
1. 55 days
2. 40 days
3. 45 days
4. 60 days
Answers
1. (2) 2. (2) 3. (2) 4. (1) 5. (2)